Where the four active contracts stand, what ships between now and month-end, and the calendar that lands us at the August 31 Chamber of Health Partners Launch.
Four contracted workstreams are in flight. Two are complete; two culminate in early August, clearing the runway for the Aug 31 launch.
Milestone dates are drawn from the four SCFA project boards. Green = delivered · red = today · gold = upcoming.
The month the deliverables close and the launch lands.
Runway activities (Aug 6–28) are the recommended launch-prep cadence and are yours to move; the two August milestones and the Aug 31 launch are the fixed anchors.
| Item | Status | Note |
|---|---|---|
| Live-data pipeline for the Public Impact dashboard | Watch | Must be validated and stable before it's the partner-facing centerpiece on Aug 31. |
| Banner pilot data → shareable proof points | Watch | De-identified only; final report lands Aug 5, leaving 3+ weeks to package for partners. |
| Chamber of Health partner roster | On track | Group infrastructure delivered in C1; confirm committed partners by mid-Aug. |
| Website Redesign (C4) go/no-go | Decision | If greenlit, scope so it doesn't compete with launch-prep bandwidth. |
Two of four contracts are delivered and paid. The remaining two both close in the first week of August — eight clear weeks before, then three-plus weeks of runway before the Aug 31 Chamber of Health Partners Launch. Nothing critical lands after Aug 5, so the launch window is protected. The single most important thing to lock is the live-data Public Impact dashboard, which is the partner-facing story on launch day.